KP Energy secures order from Aditya Birla Renewables
Aditya Birla Renewables has given K P Energy the go-ahead to install the balance of plant for a 23.1 MW wind energy project. The order's worth was not, however, made public by the business.
The term "balance of plant" describes a variety of auxiliary and supporting parts of a power installation.
"K P Energy has received a new order from Aditya Birla Renewables for development of Balance of Plant of 23.1MW wind capacity forming part of the wind-solar hybrid power project (comprising 23.1MW wind and 11MW solar) to be connected to existing 140MW power evacuation facility at Fulsar PSS," a BSE filing stated.
The project includes installation of 11 Suzlon-made wind mills.
K P Energy will be responsible for providing a range of services, including Engineering, Procurement, Construction, and Commissioning (EPCC) for the project.